Environmental Projects
Click on a link below to see a slideshow with information on the project.
(Internet Explorer users: click the left and right sides of the slides to move through the slideshows.)
Washington Closure Hanford - 100 B Reactor Roof Repair and Replacement
Washington Closure Hanford - 100 B Reactor Roof Repair and Replacement
$1.1 million
2008
B Reactor as it stood at the height of its production days.
Washington Closure Hanford - 100 B Reactor Roof Repair and Replacement
Washington Closure Hanford - 100 B Reactor Roof Repair and Replacement
$1.1 million
2008
FE&C personnel suited in personal protective equipment (PPE) and fall protection equipment.
Washington Closure Hanford - 100 B Reactor Roof Repair and Replacement
Washington Closure Hanford - 100 B Reactor Roof Repair and Replacement
$1.1 million
2008
FE&C carefully working to replace and repair the B Reactor’s roof sections.
Washington Closure Hanford - 100 B Reactor Roof Repair and Replacement
Washington Closure Hanford - 100 B Reactor Roof Repair and Replacement
$1.1 million
2008
FE&C worker checks his fall protection equipment.
Bechtel - 100 B/C Burial Grounds and 100 B/C Remaining Piplines and Sewers (RPAS)
Bechtel - 100 B/C Burial Grounds and 100 B/C Remaining Piplines and Sewers (RPAS)
$32.0 million
2004 - 2007
Every workday begins with a plan of the day meeting.
Bechtel - 100 B/C Burial Grounds and 100 B/C Remaining Piplines and Sewers (RPAS)
Bechtel - 100 B/C Burial Grounds and 100 B/C Remaining Piplines and Sewers (RPAS)
$32.0 million
2004 - 2007
Loadout of contaminated soil.
Bechtel - 100 B/C Burial Grounds and 100 B/C Remaining Piplines and Sewers (RPAS)
Bechtel - 100 B/C Burial Grounds and 100 B/C Remaining Piplines and Sewers (RPAS)
$32.0 million
2004 - 2007
Backfilling the pit after remediation of all hazardous materials.
Bechtel - 100 B/C Burial Grounds and 100 B/C Remaining Piplines and Sewers (RPAS)
Bechtel - 100 B/C Burial Grounds and 100 B/C Remaining Piplines and Sewers (RPAS)
$32.0 million
2004 - 2007
Radwaste Solutions Magazine, March/April 2005, © 2005 by the American Nuclear Society, used with permission.
Bechtel - 100 B/C Burial Grounds and 100 B/C Remaining Piplines and Sewers (RPAS)
Bechtel - 100 B/C Burial Grounds and 100 B/C Remaining Piplines and Sewers (RPAS)
$32.0 million
2004 - 2007
A backhoe excavates the 100 B/C reactors’ twin box sewer.
Bechtel - 100 B/C Burial Grounds and 100 B/C Remaining Piplines and Sewers (RPAS)
Bechtel - 100 B/C Burial Grounds and 100 B/C Remaining Piplines and Sewers (RPAS)
$32.0 million
2004 - 2007
Gas cylinders excavated at the burial grounds.
Bechtel - 100 B/C Burial Grounds and 100 B/C Remaining Piplines and Sewers (RPAS)
Bechtel - 100 B/C Burial Grounds and 100 B/C Remaining Piplines and Sewers (RPAS)
$32.0 million
2004 - 2007
A “mountain” of contaminated buried reactor hardware and soil.
Bechtel - 100 B/C Burial Grounds and 100 B/C Remaining Piplines and Sewers (RPAS)
Bechtel - 100 B/C Burial Grounds and 100 B/C Remaining Piplines and Sewers (RPAS)
$32.0 million
2004 - 2007
Overburden stockpiling.
Bechtel - 100 B/C Burial Grounds and 100 B/C Remaining Piplines and Sewers (RPAS)
Bechtel - 100 B/C Burial Grounds and 100 B/C Remaining Piplines and Sewers (RPAS)
$32.0 million
2004 - 2007
Workforce wearing Personal Protective Equipment (PPE) is a common sight at 100 B/C.
Bechtel - 100 B/C Burial Grounds and 100 B/C Remaining Piplines and Sewers (RPAS)
Bechtel - 100 B/C Burial Grounds and 100 B/C Remaining Piplines and Sewers (RPAS)
$32.0 million
2004 - 2007
Nuclear reactor thimbles were just some of the surprises remediated at 100 B/C.
Bechtel - 100 B/C Burial Grounds and 100 B/C Remaining Piplines and Sewers (RPAS)
Bechtel - 100 B/C Burial Grounds and 100 B/C Remaining Piplines and Sewers (RPAS)
$32.0 million
2004 - 2007
Aerial view of Hanford B-Reactor site, June 1944.
Washington Closure Hanford (subcontractor to Foothills Environmental) - 100 B/C Remaining Sites Remedial Action
Washington Closure Hanford (subcontractor to Foothills Environmental) - 100 B/C Remaining Sites Remedial Action
$2.9 million
2008-2009
An aerial view of the finished project – completion of all excavation and remediation.
Washington Closure Hanford (subcontractor to Foothills Environmental) - 100 B/C Remaining Sites Remedial Action
Washington Closure Hanford (subcontractor to Foothills Environmental) - 100 B/C Remaining Sites Remedial Action
$2.9 million
2008-2009
Piping with liquid hexavalent chromium was a part of this remediation.
Washington Closure Hanford (subcontractor to Foothills Environmental) - 100 B/C Remaining Sites Remedial Action
Washington Closure Hanford (subcontractor to Foothills Environmental) - 100 B/C Remaining Sites Remedial Action
$2.9 million
2008-2009
Excavating chromium pipline.
Washington Closure Hanford (subcontractor to Foothills Environmental) - 100 B/C Remaining Sites Remedial Action
Washington Closure Hanford (subcontractor to Foothills Environmental) - 100 B/C Remaining Sites Remedial Action
$2.9 million
2008-2009
Chasing a chromium spill, at an excavation depth of 45 feet.
Washington Closure Hanford (subcontractor to Foothills Environmental) - 100 B/C Remaining Sites Remedial Action
Washington Closure Hanford (subcontractor to Foothills Environmental) - 100 B/C Remaining Sites Remedial Action
$2.9 million
2008-2009
Chemically contaminated reinforced concrete structures waiting to be demolished, size-reduced and containerized.
Washington Closure Hanford (subcontractor to Foothills Environmental) - 100 B/C Remaining Sites Remedial Action
Washington Closure Hanford (subcontractor to Foothills Environmental) - 100 B/C Remaining Sites Remedial Action
$2.9 million
2008-2009
Chemical waste tanks excavated near the C Reactor.
Washington Closure Hanford - 100 F Burial Grounds Remediation
Washington Closure Hanford - 100 F Burial Grounds Remediation
$13.7 million
2005-2008
F Reactor, in its present cocooned state.
Washington Closure Hanford - 100 F Burial Grounds Remediation
Washington Closure Hanford - 100 F Burial Grounds Remediation
$13.7 million
2005-2008
The 100F site early in remediation efforts.
Washington Closure Hanford - 100 F Burial Grounds Remediation
Washington Closure Hanford - 100 F Burial Grounds Remediation
$13.7 million
2005-2008
Pipeline excavation.
Washington Closure Hanford - 100 F Burial Grounds Remediation
Washington Closure Hanford - 100 F Burial Grounds Remediation
$13.7 million
2005-2008
Transporting roll-off containers.
Washington Closure Hanford - 100 F Burial Grounds Remediation
Washington Closure Hanford - 100 F Burial Grounds Remediation
$13.7 million
2005-2008
Excavation of a buried railcar.
Washington Closure Hanford - 100 F Burial Grounds Remediation
Washington Closure Hanford - 100 F Burial Grounds Remediation
$13.7 million
2005-2008
Sealing and tarping of a container to prepare it for transport to ERDF.
Washington Closure Hanford - 100 F Burial Grounds Remediation
Washington Closure Hanford - 100 F Burial Grounds Remediation
$13.7 million
2005-2008
Cassion removal.
Washington Closure Hanford - 100 F Burial Grounds Remediation
Washington Closure Hanford - 100 F Burial Grounds Remediation
$13.7 million
2005-2008
A pile of highly radioactive fuel spacers after being excavated.
Washington Closure Hanford - 100 F Burial Grounds Remediation
Washington Closure Hanford - 100 F Burial Grounds Remediation
$13.7 million
2005-2008
The Container Transfer Area (CTA).
Washington Closure Hanford - 100 F Burial Grounds Remediation
Washington Closure Hanford - 100 F Burial Grounds Remediation
$13.7 million
2005-2008
A spill kit is ready and waiting for any hazards. FE&C has had noradioactive contamination incidents in the company's history.
Washington Closure Hanford - 100 H Burial Grounds and Remaining Sites Remediation
Washington Closure Hanford - 100 H Burial Grounds and Remaining Sites Remediation
$9.4 million
2008-2010
The 100 H area from an aerial view.
Washington Closure Hanford - 100 H Burial Grounds and Remaining Sites Remediation
Washington Closure Hanford - 100 H Burial Grounds and Remaining Sites Remediation
$9.4 million
2008-2010
An excavator loads a roll-off truck for transport.
Washington Closure Hanford - 100 H Burial Grounds and Remaining Sites Remediation
Washington Closure Hanford - 100 H Burial Grounds and Remaining Sites Remediation
$9.4 million
2008-2010
A sign in the field office at 100H details the number of days on project without a lost-time accident.
Washington Closure Hanford - 100 H Burial Grounds and Remaining Sites Remediation
Washington Closure Hanford - 100 H Burial Grounds and Remaining Sites Remediation
$9.4 million
2008-2010
The FE&C team achieves the STAR award.
CH2M Hill - 100 K Remedial Action
CH2M Hill - 100 K Remedial Action
$15 million
2009-2012
Excavation holes in the 100 K area as remediated by FE&C.
CH2M Hill - 100 K Remedial Action
CH2M Hill - 100 K Remedial Action
$15 million
2009-2012
Heavy equipment is being used on structures in the shadow of the reactor.
CH2M Hill - 100 K Remedial Action
CH2M Hill - 100 K Remedial Action
$15 million
2009-2012
A concrete structure is undergoing size reduction in order to meet waste acceptance criteria.
CH2M Hill - 100 K Remedial Action
CH2M Hill - 100 K Remedial Action
$15 million
2009-2012
Roll-off waste containers filled with contamination awaiting transportation.
CH2M Hill - 100 K Remedial Action
CH2M Hill - 100 K Remedial Action
$15 million
2009-2012
Construction of the Waste Transfer Area.
Washington Closure Hanford (subcontractor to Phoenix Enterprises) - 100 N Remedial Action
Washington Closure Hanford (subcontractor to Phoenix Enterprises) - 100 N Remedial Action
$7.8 million
2010-present
Historic aerial view of the N Reactor site.
Washington Closure Hanford (subcontractor to Phoenix Enterprises) - 100 N Remedial Action
Washington Closure Hanford (subcontractor to Phoenix Enterprises) - 100 N Remedial Action
$7.8 million
2010-present
Overburden removal from one of the waste sites.
Washington Closure Hanford (subcontractor to Phoenix Enterprises) - 100 N Remedial Action
Washington Closure Hanford (subcontractor to Phoenix Enterprises) - 100 N Remedial Action
$7.8 million
2010-present
Remediation activities during the winter months continues.
Washington Closure Hanford (subcontractor to Phoenix Enterprises) - 100 N Remedial Action
Washington Closure Hanford (subcontractor to Phoenix Enterprises) - 100 N Remedial Action
$7.8 million
2010-present
A haul truck enters the survey and tarping station for waste packaging operations.
Washington Closure Hanford (subcontractor to Sage Tec) - 100-C-7 “Big Dig” Remediation
Washington Closure Hanford (subcontractor to Sage Tec) - 100-C-7 “Big Dig” Remediation
$3 million
2011-2012
The site before FE&C's remediation.
The 100-C-7 waste sites are approximately 1115 ft west of the C reactor building and consist of the residual contaminant sodium dichromate, which is considered hazardous and is a known carcinogen. This sodium dichromate is associated with concrete that was left in place after the 1997 decommissioning of the water treatment facility's filter pump room. Remedial actions in 2004 found chromium-stained surface soil at 100-C-7-1. These waste sites are less than a mile from the Columbia River.
Washington Closure Hanford (subcontractor to Sage Tec) - 100-C-7 “Big Dig” Remediation
Washington Closure Hanford (subcontractor to Sage Tec) - 100-C-7 “Big Dig” Remediation
$3 million
2011-2012
During excavation. To put the scope in perspective, B Reactor in the upper portion and C Reactor is right and center.
Once the project began, it was found that contamination depths of hexavalent chromium was greater than expected. Increasing the depth of the excavations increased the size of the excavation at ground level. Because there were additional concrete foundations in these new areas, they had to be abated and removed. These foundations contained piping with asbestos insulation. The expanded remediation also contained overhead power lines and poles, which needed to be relocated.
Washington Closure Hanford (subcontractor to Sage Tec) - 100-C-7 “Big Dig” Remediation
Washington Closure Hanford (subcontractor to Sage Tec) - 100-C-7 “Big Dig” Remediation
$3 million
2011-2012
Closer view, showing the stadium-like depths of the dig.
Additionally, the levels and concentration of hexavalent chromium are higher than were expected, which has required additional sorting as well as special packaging and shipping. The project also included the recycling and reuse of large quantities of material including concrete, piping, rebar, grating and structural steel.
Bechtel - 105D Reactor Safe Storage Enclosure
Bechtel - 105D Reactor Safe Storage Enclosure
$2.4 million
2003-2004
Bechtel - 105D Reactor Safe Storage Enclosure
Bechtel - 105D Reactor Safe Storage Enclosure
$2.4 million
2003-2004
D reactor before coccooning operations began.
Bechtel - 105D Reactor Safe Storage Enclosure
Bechtel - 105D Reactor Safe Storage Enclosure
$2.4 million
2003-2004
Demolition phase.
Bechtel - 105D Reactor Safe Storage Enclosure
Bechtel - 105D Reactor Safe Storage Enclosure
$2.4 million
2003-2004
Wrench motors for control rods.
Bechtel - 105D Reactor Safe Storage Enclosure
Bechtel - 105D Reactor Safe Storage Enclosure
$2.4 million
2003-2004
Careful demolition of the block walls inside the reactor.
Bechtel - 105D Reactor Safe Storage Enclosure
Bechtel - 105D Reactor Safe Storage Enclosure
$2.4 million
2003-2004
Construction of steel. Project risk management included large cranes and extreme heights.
Bechtel - 105D Reactor Safe Storage Enclosure
Bechtel - 105D Reactor Safe Storage Enclosure
$2.4 million
2003-2004
The near-completed safe storage enclosure, or cocoon, around the 105D reactor.
Washington Closure Hanford (subcontractor to Sage Tec) - 309 and 300 Area Remaining Waste Sites
Washington Closure Hanford (subcontractor to Sage Tec) - 309 and 300 Area Remaining Waste Sites
$15 Million
2012 - present
Highly contaminated research facilities in the 300 Area are located near the Columbia River. Photo credit WCH.
Washington Closure Hanford (subcontractor to Sage Tec) - 309 and 300 Area Remaining Waste Sites
Washington Closure Hanford (subcontractor to Sage Tec) - 309 and 300 Area Remaining Waste Sites
$15 Million
2012 - present
Recent picture of the 300 Area.
Washington Closure Hanford (subcontractor to Sage Tec) - 309 and 300 Area Remaining Waste Sites
Washington Closure Hanford (subcontractor to Sage Tec) - 309 and 300 Area Remaining Waste Sites
$15 Million
2012 - present
the team will be responsible for demolition of the shell of the 309 reactor (the dome, pictured here, was removed previously).
Washington Closure Hanford (subcontractor to Sage Tec) - 309 and 300 Area Remaining Waste Sites
Washington Closure Hanford (subcontractor to Sage Tec) - 309 and 300 Area Remaining Waste Sites
$15 Million
2012 - present
The site contains both radiological and chemical radiation.
Bechtel - 618-4 and 618-5 Burial Grounds Remediation
Bechtel - 618-4 and 618-5 Burial Grounds Remediation
$4.3 million
2002-2003
The 300 area today.
Bechtel - 618-4 and 618-5 Burial Grounds Remediation
Bechtel - 618-4 and 618-5 Burial Grounds Remediation
$4.3 million
2002-2003
Personnel in Level B Personal Protective Equipment (PPE).
Bechtel - 618-4 and 618-5 Burial Grounds Remediation
Bechtel - 618-4 and 618-5 Burial Grounds Remediation
$4.3 million
2002-2003
Soil remediation was also part of this job.
Other building products
Bechtel - 618-4 and 618-5 Burial Grounds Remediation
Bechtel - 618-4 and 618-5 Burial Grounds Remediation
$4.3 million
2002-2003
Buried drums from 1940-1950 contained (left) graphite and uranium chips and (right) uranium chips and oil.
Bechtel - 618-4 and 618-5 Burial Grounds Remediation
Bechtel - 618-4 and 618-5 Burial Grounds Remediation
$4.3 million
2002-2003
Workers learn special handling methods on how to to transport and overpack 50-year-old drums of uranium chips.
Bechtel - 618-4 and 618-5 Burial Grounds Remediation
Bechtel - 618-4 and 618-5 Burial Grounds Remediation
$4.3 million
2002-2003
A pile of soil that contained spent nuclear fuel rods from inside a reactor.
Syncrude Canada - Ft. McMurray, Alberta Demolition and Salvage
Syncrude Canada - Ft. McMurray, Alberta Demolition and Salvage
$1.5 million
2008
Syncrude’s tower, before demolition.
Syncrude Canada - Ft. McMurray, Alberta Demolition and Salvage
Syncrude Canada - Ft. McMurray, Alberta Demolition and Salvage
$1.5 million
2008
The same tower, during demolition.
Syncrude Canada - Ft. McMurray, Alberta Demolition and Salvage
Syncrude Canada - Ft. McMurray, Alberta Demolition and Salvage
$1.5 million
2008
Crumpled staircases during demolition, looking a lot like an MC Esher optical illusion.
Fortune Minerals - Golden Giant Mine Decommissioning and Demolition
Fortune Minerals - Golden Giant Mine Decommissioning and Demolition
$19 million
2008-2009
The 1.9 million square feet of Golden Giant Mine, before FE&C completely demolished the facility.
Fortune Minerals - Golden Giant Mine Decommissioning and Demolition
Fortune Minerals - Golden Giant Mine Decommissioning and Demolition
$19 million
2008-2009
Siding is carefully dismantled with the use of man-lifts and cranes.
Fortune Minerals - Golden Giant Mine Decommissioning and Demolition
Fortune Minerals - Golden Giant Mine Decommissioning and Demolition
$19 million
2008-2009
Very large cranes were used on this project.
Fortune Minerals - Golden Giant Mine Decommissioning and Demolition
Fortune Minerals - Golden Giant Mine Decommissioning and Demolition
$19 million
2008-2009
Demolition used very large equipment.
Fortune Minerals - Golden Giant Mine Decommissioning and Demolition
Fortune Minerals - Golden Giant Mine Decommissioning and Demolition
$19 million
2008-2009
Immediately after the use of explosive demolition.
Washington Closure Hanford (subcontractor to Phoenix Enterprises) - IU 2 & 6 and 100 H Remedial Action
Washington Closure Hanford (subcontractor to Phoenix Enterprises) - IU 2 & 6 and 100 H Remedial Action
$13.6 million
2009-present
Workers carefully excavate an archeological site near the original Hanford Construction Camp for any remaining artifacts.
Washington Closure Hanford (subcontractor to Phoenix Enterprises) - IU 2 & 6 and 100 H Remedial Action
Washington Closure Hanford (subcontractor to Phoenix Enterprises) - IU 2 & 6 and 100 H Remedial Action
$13.6 million
2009-present
Excavators remediating structural and soil waste at 100 H.
Washington Closure Hanford (subcontractor to Phoenix Enterprises) - IU 2 & 6 and 100 H Remedial Action
Washington Closure Hanford (subcontractor to Phoenix Enterprises) - IU 2 & 6 and 100 H Remedial Action
$13.6 million
2009-present
Road construction and maintenance is part of this project.
Washington Closure Hanford (subcontractor to Phoenix Enterprises) - IU 2 & 6 and 100 H Remedial Action
Washington Closure Hanford (subcontractor to Phoenix Enterprises) - IU 2 & 6 and 100 H Remedial Action
$13.6 million
2009-present
Excavators remediating structural and soil waste at IU 2 & 6.
Washington Closure Hanford (subcontractor to Phoenix Enterprises) - IU 2 & 6 and 100 H Remedial Action
Washington Closure Hanford (subcontractor to Phoenix Enterprises) - IU 2 & 6 and 100 H Remedial Action
$13.6 million
2009-present
Management is on site almost daily to communicate with project personnel.
Washington Closure Hanford (subcontractor to Phoenix Enterprises) - IU 2 & 6 and 100 H Remedial Action
Washington Closure Hanford (subcontractor to Phoenix Enterprises) - IU 2 & 6 and 100 H Remedial Action
$13.6 million
2009-present
Excavators uncover and size-reduce contaminated foundations at 100H.
Washington Closure Hanford (subcontractor to Phoenix Enterprises) - IU 2 & 6 and 100 H Remedial Action
Washington Closure Hanford (subcontractor to Phoenix Enterprises) - IU 2 & 6 and 100 H Remedial Action
$13.6 million
2009-present
Excavators uncover and size-reduce contaminated foundations at 100H.